# Change Over

A changeover is the time between the last good part of one product and the first good part of the next. Kanoa counts it as
its own mode, **Changeover**, so the time isn't held against either run, and so your plant can see how long changeovers
really take.

## Put the Machine into Changeover

1. Tap the **Production** card to open **Run Control**.
2. Change the mode to **Changeover**, and close Run Control.

The **Production** card now shows *Changeover*. The run you were on has ended.

## Swap the Tool

Skip this section if your machine doesn't use molds or dies. On machines that do, a **Tooling** card on the info panel shows
the tool that's mounted, such as *Tooling Installed - M-100 - 4 parts/cycle*. Kanoa measures the run against the mounted
tool's rate, so the tool in Kanoa has to match the one in the machine.

1. Tap the **Tooling** card. The **Tooling** popup opens on its **Mount / Unmount** tab.
2. Select the mounted tool, and unmount it.
3. Under **Mount a tool**, pick the new tool as the **Tool**, and leave **Into** as *On the machine*.
4. Leave **Mounted at** empty, so the tool is mounted now, and click **Mount**.
5. Close the popup. The **Tooling** card shows the new tool.

![Mount panel](https://docs.kanoa.ai/img/tooling/mount-panel.png)

If you mount a tool before putting the machine into Changeover, Kanoa asks whether to switch to Changeover first. Say yes:
setting a tool is changeover time, not production.

:::warning[Mount warnings]
If the tool is due for maintenance or over a limit, a **Mount warnings** popup opens. Don't just click **OK**: tell your
supervisor or maintenance first. **OK** mounts the tool anyway and saves the warning with the mount. **Close** mounts
nothing.
:::

The **Tooling** card's stripe is green while the tool is within its limits, orange when it's due for maintenance, and red
when it's over a limit.

::embed-section{src="../../kanoa-ops/tooling/mounting.md" collapsed="true" summary="Reference Materials: Mounting Tools - The mount panel, mount rules and warnings."}

## Start the Next Run

When the machine is set up, start the next run from **Run Control**, as in [Run Production](./2-run-production.md): pick
the next order on the **Orders** tab, or the product on the **Product** tab, and click **Start Run**. The changeover ends
when the run starts.

## Check Your Understanding

1. Why does Kanoa count changeover as its own mode?
2. You've mounted a new mold and a Mount warnings popup opens. What do you do?

<details>
<summary>Answers</summary>

1. So changeover time isn't held against either run, and the plant can see how long changeovers take.
2. Don't click **OK** straight away: tell your supervisor or maintenance about the warning first.

</details>