Code Performance Events

Machine 1 already has a speed loss built in. Its standard rate is 3.75 lbs/min, but the simulator feeds it at only about 3.25 lbs/min, which matches the scheduled rate you configured in Configure Production Rates. Expected infeed is always based on the standard rate, so every minute Machine 1 runs, Kanoa counts the gap between expected and actual infeed as lost time.

Runtime: 60 min
Expected infeed: 60 × 3.75 = 225 lbs
Actual infeed: 60 × 3.25 = 195 lbs
Missing infeed: 30 lbs → 30 ÷ 3.75 = 8 lost minutes

Speed loss is measured on the infeed, because it is lost process time, not lost output. Time the machine was stopped is downtime and is handled by state events, not performance events.

Code the lost minutes
  1. Navigate to Ops → Operations → Performance Events.
  2. Select Machine 1 and today's date range, then run the report.

Review the rows in the upper table. Each one shows the runtime, expected and actual infeed, and the lost minutes Kanoa calculated, with any uncoded time still open.


  1. Select a row and click the add button.
  2. Choose Tool Wear, enter part of the lost minutes (for example, half), and add a note such as Feed reduced after insert change was postponed.
  3. Save, then add a second event for the remaining minutes using Material Hardness Variation.
  4. Confirm the row no longer shows uncoded lost time.
Code a speed loss as it happens

Machine 1 runs at about 87% of its standard rate, so Kanoa also records its speed loss as it happens: after 5 minutes below 95% of the standard, an automatic performance event opens on the run.

  1. Open Machine 1's Asset Operation screen. Under the state card, the info panel shows a speed loss card, such as Below standard: 87% of the standard rate · Unassigned.
  2. Tap the card. In the Set Speed Loss tree, open Machining, select Material Hardness Variation, add a note and click Save.
  3. The card now shows the reason, with its colour on the card's stripe.

Minutes you already coded by hand on the same run take precedence: the automatic event's overlapping minutes are left out of the reports, so nothing is counted twice. On the shop floor, setting the reason on the card is usually all an operator needs to do. See Speed Loss.

Kanoa doesn't create the loss when you code it. The loss already exists in the OEE performance number. Coding only explains it, so the same minutes can be split across several reasons when more than one thing slowed the line.

tip

Code performance events while the details are fresh, ideally at the end of each shift. Reasons can also be written by script with system.kanoa.event.addPerformanceEvent when a machine or supervisory system already reports why it slowed down.

Chart performance reasons
  1. Open the dashboard you built in Build a Dashboard, or create a new one named Machining Performance.
  2. Add the Analytics/Performance Reason Pie Chart widget and the Analytics/Performance Reason Table widget.
  3. Select Machine 1 and today in the dashboard's asset and date range selectors (if you created a new dashboard, add these selectors first, as in Build a Dashboard), and confirm your coded minutes appear by reason.