Kanoa Quality Knowledge Check
Use these questions to check your understanding of Kanoa Quality and to prepare for the certification exam.
What is the difference between a check sheet and a check event?
The check sheet is the reusable template. A check event is one occurrence of it being started and filled in, with its own status and answers. See Fill Out The Check Sheet.
An operator answers Passable for every area of the Cleanliness Check. Is the check OK?
Yes. Passable is a Warning, and only a Fail on a check item makes the check not OK. See Build the Check Sheet.
Can an operator run a check sheet that is still in Draft?
No. The list of check sheets you can add a check from shows only enabled, Released sheets, to every user, Gateway Admins included. To try out a Draft sheet, a Gateway Admin or a user with Configure Quality can select it in Configuration → Quality → Check Sheets and click Launch Check Sheet, which opens a test check that's deleted when you close it. See Build the Check Sheet.
When is an answer saved: when it's entered, or when the check is submitted?
When it's entered. Submit completes the check and changes its status. See Fill Out The Check Sheet.
A check sheet doesn't require a sign-off. What status does a submitted check end in?
Approved. It passes straight through Submitted. See Check Sheet Timers.
What moves a check nobody has started from Coming Due to Missed?
Its trigger's timers: Delay, Coming Due, Over Due and Grace. See Check Sheet Timers.
Why point a check item at an attribute instead of a tag path?
The attribute's data sources map it to a different tag for each asset, so one check sheet design works on every line and its builders don't need tag paths. See Attributes for Tag Data.
What does an Auto check sheet need to complete itself?
Asset Required, and an attribute with an enabled data source for that asset on every required check item. See Automatic Checks on a Timer.
Timed checks aren't appearing. What do you check first?
The Quality Schedule gateway timer, on the Timers tab of the Kanoa gateway config page (Kanoa > Settings). Then check that the sheet is released, the trigger is enabled, and the data sources are enabled. See Automatic Checks on a Timer.
What's the difference between specification limits and control limits?
Spec limits come from product or customer requirements and say whether the product is acceptable. Control limits are calculated from the process data and say whether the process is stable. See Coating Line SPC.
A Check Details cell is highlighted, but the value is within spec. Is that an error?
No. It marks a possible SPC rule violation, such as a trend, not a spec failure. See Analyze SPC Data with Check Details.
Which screen do you use for each question: "was this check done right?", "were checks done on time?", "is the process stable?"
Check Table, Check Summary and Check Details. See Analyze SPC Data with Check Details.
When should you use an item set instead of an item class?
When the grouping you need, such as part families that share a spec, doesn't match the item class hierarchy. Each item can be in only one item set. See Item Sets and Attribute Tolerances.
A diameter falls between the LCL and the LSL. How is it evaluated?
It passes, but is highlighted as a warning. Outside LSL/USL it fails, and outside LEL/UEL it can't be entered. See Item Sets and Attribute Tolerances.
Length readings of 150 and 205 are entered with aggregation Max and a range of 100 to 200. Does it pass?
No. The Max is 205, which is outside the range. See Build the FAI Check Sheet.
A machine enters Production, but no FAI is issued. What should you check?
That Enable Quality Triggers is on for the asset, which needs the asset to be OEE enabled, and that the check sheet is released with a Mode Change trigger for Production. Also allow for the trigger's delay. See Trigger and Notify.
Where does a triggered FAI get its asset and item?
From the production run: the asset that entered Production and the item running on it. See Trigger and Notify.
What does the Check Summary show, and what doesn't it show?
It shows how many checks were Approved, Due, Over Due, Missed, Cancelled or Rejected. It doesn't chart measured values; use Check Details for that. See Analyze Compliance.
Why is the helper check sheet built before the main one?
The main sheet's Issue Check Sheet setting can only select a check sheet that already exists and is released. See Build the Analyzer Check Sheet.
What happens when the operator clicks Get Analyzer Data and takes a measurement?
Every item whose trigger is Get Analyzer Data reads its attribute's data source tag for the QA Station at the same moment. See Build the Analyzer Check Sheet.
What does Sign Off Required change?
A submitted check stays in Submitted until a user with the Approve Checks function approves it. See Build the Analyzer Check Sheet.
Why didn't the test fail action fire on the first run?
Nothing on the sheet had a spec yet, so nothing could fail. The action only runs when a check actually fails. See Run and Validate.
Is the follow-up check issued when the failed check is submitted or when it's approved?
When it's submitted, before approval. See Run and Validate.
A Particle Size of 110 is entered against LSL 25, UCL 100 and USL 125. Pass or fail?
Pass, with a warning, because it's above the UCL but within the USL. See Run and Validate.
Why require an item from the CoreForge\RM class on the Receiving Inspection?
It ties each inspection to the material received, and limits the choice to raw materials from the existing item master. See Configure The Check Sheet.
What's the difference between Enabled and Required on a check item?
Enabled decides whether the item appears. Required decides whether the check can be submitted with it blank. See Add Check Items.
Why is ab123 rejected by the Lot Number regex?
It's only five characters and contains lowercase letters. The regex needs 6 to 20 uppercase letters or digits. See Add Check Items.
What do Neutral responses in a Text pick list do?
They record information, such as a supplier name, without passing or failing the check. See Add Check Items.
With Manual trigger timers of Over Due 30 and Grace 30, when does an untouched check you added by hand become Missed?
60 minutes after it's added: a check added by hand is Due at once, Over Due at 30 and Missed at 60. Delay and Coming Due only apply to checks a trigger schedules. See Revise and Correct.
Why must an approved check be rejected before it can be corrected?
So changing approved quality data is a deliberate step that takes the check out of Approved first. Rejecting needs the Approve Checks function. See Revise and Correct.