Plan Preventive Maintenance

Preventive maintenance (PM) happens on a regular interval. You plan it once with a Recurring template. Kanoa then generates each work order on schedule, and technicians complete them as in Preventive Maintenance.

Create the Recurring Template​

For example, CoreForge's weekly PM for Machine 1.

  1. Open Configuration → Maintenance → Work Orders and add a template on the Work Orders tab.

  2. Fill in the details:

    FieldExample
    TitleMachine 1 - Weekly PM
    AssetCoreForge\Philadelphia\Machining\Machine 1
    Maintenance typePreventive
    Work typeLubrication
    PriorityMedium
    ProcedureMachine 1 Weekly PM
    Schedule typeRecurring
  3. In the Schedule section, set the Start Date, Generate Ahead and how often to Repeat every, such as 1 Week on a chosen day. Leave Ends at Never for a PM that never stops.

Recurrence options

Schedule times follow the asset's site time zone, so a PM due at 06:00 stays at 06:00 at the plant when the clocks change.

Choose Generate Ahead​

Generate Ahead controls how far in advance work orders are created. With 7 days, next week's PM appears in the work order list a week early. Planners and technicians see the workload coming, so check the Due on date and not just whether the work order exists.

Release the Template​

  1. Save the template, then set its version status to Released.
warning

Releasing a recurring template starts real work orders, and it keeps generating them on schedule. Technicians will see them. Check the procedure, priority and schedule first. A template that is not Released is never scheduled.

Reference Materials: Schedule Types - One Time, Recurring and Condition.

Schedule Types​

A Work Order template includes a Schedule Type, which determines how work orders are generated. When a template is active i.e. 'Released', the system evaluates its schedule configuration. When the criteria are satisfied, an actual work order is created.

Kanoa Maintenance supports three primary schedule behaviors:

One Time

Use One Time when the template should generate a single work order.

This is useful for:

  • one-off repairs
  • installation work
  • project tasks
  • ad hoc maintenance requests

When a template is configured as One Time, the system generates one actual work order from that template.

Recurring

Use Recurring when the template should continuously generate work orders on a defined schedule.

This is typically used for:

  • preventive maintenance
  • routine inspections
  • repeating safety checks
  • calendar-based maintenance programs

When a template is configured as Recurring, the system creates actual work orders according to the recurrence settings. The schedule's times are in the asset's site time zone (UTC if the site has none), so a work order due at 06:00 stays at 06:00 at the plant across daylight-saving changes.

Recurring schedules are best used when maintenance should happen on a predictable interval, such as:

  • every day
  • every week
  • every month
  • every X days/hours depending on schedule configuration

kanoa-cmms

Condition

Use Condition when the template should generate work orders only after a defined asset condition, counter, or threshold is met.

This is typically used for:

  • runtime-based maintenance
  • counter-based maintenance
  • threshold-triggered inspections
  • condition-based corrective or preventive work

When a template is configured as Condition, the maintenance order can be set to be triggered whenever the asset run hours or counter values reach a certain threshold, or, for a tool, when its tool life comes due. Condition scheduling is useful for maintenance strategies that should not be driven by calendar date alone.


kanoa-cmms


kanoa-cmms


Tool Life works with Kanoa Ops tooling. It's only offered when the template's Asset is a tool, such as a mold, so select the tool first. Set Due for to the tool limit the work order covers: its PM, refurbishment or calibration. A work order is created when the tool reaches its Warn at % of that limit, and completing the work order resets that count, the same as recording it on the tool's Life tab. The tool's work orders are listed on the Maintenance tab of its tool editor.


kanoa-cmms


Reference Materials: Version Status - Why a template must be Released.

Version Status​

Work orders can be created, but will not be scheduled or used until they have been set to a 'Released' version status.

kanoa-cmms


Worked Example​

The CoreForge sample plant schedules Machine 1's weekly PM, with the procedure from Write a Procedure, the same as Developer Training.

Create the Recurring Template​

Preventive maintenance happens on a predictable interval, so it uses a Recurring template. Every work order it generates carries the Machine 1 Weekly PM procedure you wrote.

Create the recurring template
  1. In Configuration → Maintenance → Work Orders, add a template:

    FieldValue
    TitleMachine 1 - Weekly PM
    AssetCoreForge\Philadelphia\Machining\Machine 1
    Maintenance typePreventive
    Work typeLubrication
    PriorityMedium
    ProcedureMachine 1 Weekly PM
    Schedule typeRecurring
  2. In the Schedule section, set Start Date to today, Generate Ahead to 7 days, and Repeat every 1 Week on today's day of the week. Leave Ends at Never.

  3. Save and release the template.

Generate Ahead controls how far in advance work orders are created. With 7 days, next week's PM appears in the work order list a week early, so planners can see the workload coming.

Reference Materials: Schedule Types

Schedule Types​

A Work Order template includes a Schedule Type, which determines how work orders are generated. When a template is active i.e. 'Released', the system evaluates its schedule configuration. When the criteria are satisfied, an actual work order is created.

Kanoa Maintenance supports three primary schedule behaviors:

One Time

Use One Time when the template should generate a single work order.

This is useful for:

  • one-off repairs
  • installation work
  • project tasks
  • ad hoc maintenance requests

When a template is configured as One Time, the system generates one actual work order from that template.

Recurring

Use Recurring when the template should continuously generate work orders on a defined schedule.

This is typically used for:

  • preventive maintenance
  • routine inspections
  • repeating safety checks
  • calendar-based maintenance programs

When a template is configured as Recurring, the system creates actual work orders according to the recurrence settings. The schedule's times are in the asset's site time zone (UTC if the site has none), so a work order due at 06:00 stays at 06:00 at the plant across daylight-saving changes.

Recurring schedules are best used when maintenance should happen on a predictable interval, such as:

  • every day
  • every week
  • every month
  • every X days/hours depending on schedule configuration

kanoa-cmms

Condition

Use Condition when the template should generate work orders only after a defined asset condition, counter, or threshold is met.

This is typically used for:

  • runtime-based maintenance
  • counter-based maintenance
  • threshold-triggered inspections
  • condition-based corrective or preventive work

When a template is configured as Condition, the maintenance order can be set to be triggered whenever the asset run hours or counter values reach a certain threshold, or, for a tool, when its tool life comes due. Condition scheduling is useful for maintenance strategies that should not be driven by calendar date alone.


kanoa-cmms


kanoa-cmms


Tool Life works with Kanoa Ops tooling. It's only offered when the template's Asset is a tool, such as a mold, so select the tool first. Set Due for to the tool limit the work order covers: its PM, refurbishment or calibration. A work order is created when the tool reaches its Warn at % of that limit, and completing the work order resets that count, the same as recording it on the tool's Life tab. The tool's work orders are listed on the Maintenance tab of its tool editor.


kanoa-cmms


Check Your Understanding​

  1. Which schedule type do you use for a weekly PM?
  2. What does Generate Ahead do?
  3. When does a template start generating work orders?
Answers
  1. Recurring.
  2. It sets how far in advance work orders are created, so next week's PM appears early.
  3. Once its version status is Released.